Duke Energy
  • Duke Energy Generator Replacement

Charlotte NC

MEI provided a complete electrical installation for replacement of two 15 KV 1825 KW generators with replacement of the existing 15KV breakers with new ABB vacuum breakers and 15KV motor surge protectors at the gensets.

Also included were upgrades to the existing fuel supply system, additional alarms to the building management systems, and converting the existing air start system to electric.

The general contractor for this project was Luwa and the project manager was Claude Rice. Luwa project superintendent was Dakota Cleveland.

Duke Energy